Utility-plan draft expected in November as water-price questions remain
Appomattox expects a draft of its master utility plan in November, but the price of future purchased water remains unresolved as the town weighs its supply options, officials told Town Council on October 13.
Town Facilities Project Director Tori Rothgeb said the water model had been completed and work was continuing on the sewer model. The town has been working with consultants CHA and Raftelis, assembling historical data and examining future needs, including wells and purchased water.
Town Manager Michael Campbell emphasized that November’s expected delivery would be a draft for staff review, not a finished plan. Staff would examine it closely, potentially conduct fieldwork, request changes and then obtain a final version.
A separate uncertainty is the cost of water under negotiations involving Appomattox County, Campbell County and CCUSA. Campbell said the process for determining the water rate remained a sticking point. He described an expectation that an agreement could be ready by the end of October, but did not report an executed agreement or an established price.
Campbell expected a new rate for purchased water to be substantially higher than the town currently pays. He also said he believed council would expect the county to pass the water cost through without adding a markup, if the town continued purchasing that water. That was an outlook on a future supply cost, not an adopted change to residents’ water bills.
Meanwhile, well investigations are continuing. Rothgeb said yield testing had been completed at well No. 1 in Walton Place and upgrades to that well house were moving forward. Results for a well on Jones Street were still pending.
She also described plans to use cameras to examine fractures in the aquifer as part of further well work. Preliminary yield assessment, water-quality testing and more extensive testing would help determine whether a source was worth pursuing. No new well-yield figures were presented during the update.
Rothgeb said staff was also looking for funding opportunities for Confederate Boulevard, including discussions with parties beyond CHA. She did not announce a funding award.